Rochas Okorocha reign of fraud and deceit on road revolution contractors
Headlines, Imo, State News Friday, December 14th, 2012On Monday, November 19, 2012, the Honourable Commissioner for Information
and Strategy, Chinedu Offor, in an interactive program on one of the
Radio Stations in Owerri stated that contractors who had been paid
without doing their work will be arrested and prosecuted. The
Rescue Mission Government of the State claims it had already expended
13.9 billion Naira in Rochas Okorocha’s Road Revolution.
In
interviewing over 30 contractors involved in the so called Rochas Road
Revolution, I was made to understand that the actual contract document
is in the custody of the Ministry of Works. That no contractor was given an original or a duplicate copy of the contract document. However, they all stated that the following terms were contained in the original contract document.
1. Tarring of nineteen (19 km) Kilometers of road.
2. No
mobilization fee however upon the completion of 30% of the contract,
the contractor will then be paid to the extent of work completed.
3. Contract prize for one kilometer of road tarred is N120 million
These
contractors, without the traditional financial mobilization, did
mobilize to site and commenced work in earnest, believing that they have
a valid enforceable contract from Imo Government.
But the intent abnitio, the governor was never to pay these contractors. Any contract over a certain amount and or a contract that cannot be completed within a year is subject to the status of frauds. Status
of fraud is a legal term that makes a perfectly valid contract
unenforceable if the contract is not memorialized in a contract
document. Although, these contractors claimed to
have a memorialized agreement but the agreement is in the custody of the
Ministry of Works. But since they do not have a copy of such agreement and cannot produce the agreement if needed, they are out of luck.
The
doctrine of status of frauds was originally adopted under common law to
avert the infirmities emanating from human memory in situations where
the completion of a contract would take a year or more, and in
situations where the amount involved in a contract is such sum that
nobody could part with due to the mistake of he said, she said. To
avoid this from happening in contract, the doctrine of status of fraud
required that every contract of a certain sum, and all contracts that
cannot be completed within a year regardless of the sum, must be
memorialized in written document.
Essentially,
the doctrine of status of fraud designed to avert fraud may have aided
the government in perpetrating fraud on the Rochas Road Revolution
Contractors.
While
in the process of executing their road contracts, about six to eight
months into the contracts, the contractors were summoned by the
Governor, and in the course of his address to them, he informed them
that not every road currently under contract will be tarred. He
informed them that due to the enormity of the cost and the amount of
roads under the scheme, that he had decided to assign grades to each
road. Only roads assigned as grade “A” roads will
be tarred, Grade ‘B’ road will only be primed and undergo grading. “C”
roads will be graded.
As
a result of the denominations assigned to these roads, the contract
cost of one kilometer of road is now reduced to N60 million. The contract cost of the Grade “A” roads will remain as agreed. The
contractors were not happy with the unilateral modification of the
agreement by the Governor, however they all returned back to work to
complete the thirty percent (30%) work needed before payment as
originally agreed.
This
unilateral modification of the original agreement by the Governor,
shows that the Rescue Mission Government of Owelle Rochas Okorocha never
intended completing these road projects from the get go. It must be recalled, that the frenzy of these road projects commenced in the middle of the tribunal litigation.
Between September and November 2011, the entire Imo State was turned into a giant road construction site. “Construction on-going” became the watch word of Rescue Mission fanatics in the state. These were later christened Rochas Road Revolution.
But at each instant, I took time to caution my friends involved in the road construction bonanza. My
fear at all times was if the Federal Government’s capital
infrastructural budget was less then N500 Billion, how can Imo, a State
completely dependent on allocation from the Federation, afford to pay
over 300 contractors each with a contract for 19 kilometer of road at
N120 million per kilometer, the alleged original prize. Nineteen
kilometers of road multiplied by at least 300 contractors, will give
6,600 kilometers of road approximately under Rochas Road Revolution. Six thousand, six hundred kilometers of road at the original price of hundred and twenty million (N120,000,000.00) Naira per kilometer comes to over Seventy nine Billion, two hundred million naira.
Based
on this rough calculation, I concluded that there was no intent by the
Government to complete this roads, and since the contractors agreed to
mobilize to site and commence work without the traditional mobilization
in road contracts, that they would not be paid. Based on this cursory assessment, I advised my friends engaged in the road contracts to be very careful. But most ignored me.
How
can any responsible government whose total annual income is less than
N100 billion engage in road construction totaling over N80 billion?
It was on the above basis that I advised my friends involved in the purported Rochas Road Revolution (RRR)) to be careful. I especially discussed the above details with my closet friend who had mortgaged a
property for 10.5 million naira, plus another N10 million naira from
his savings which he claimed to have sunk into the road contracts in
order to meet the thirty (30%) percent needed before payment is made.
But
upon the conclusion of the meeting between the contractors and the
Governor, where the Governor allegedly unilaterally modified the
agreement, I received several calls from my road contractor friends. The
substance of what they said in these phone calls was that now the
Governor had unilaterally reduced the contract amount for a kilometer of
road to N60 m, it means that the state intends to pay them.
Not wanting to engage in any legal argument, I just listened and did not offer any legal opinion. But
I did call my close friend who had mortgaged a property in order to
complete the 30% required of the contract before payment. I
told to him to immediately use every available resources within his
control to ensure that he is paid something, anything as soon as
possible. I then told him that the claimed
modification of the road contracts by the Governor is not valid and
therefore, not legally enforceable.
A valid contract modification must have legal consideration to be enforceable. But
the said modification by the Governor does not have legal consideration
coupled with the fact that the original contract itself may not be
enforceable for want of memorialization in accordance with the status of
frauds. I told him that legal consideration must be evidenced for a valid modification to be enforced by any court.
Legal
consideration is something, (such as an act, a forbearance, or a return
promise) bargained for and received by a promissory from a promise. In layman’s term, the Governor must give something or forgo something for the modification to be valid and enforceable. But
in this case, the state did not give the contractors any additional
thing to get away with reducing the contract price of one kilometer of
road from N120 million to N60 million.
I
finally told my close friend that although the original contract and
the purported modification may not be valid and enforceable, still they
may be able to recoup some of their money through the doctrine of
detrimental reliance. The only difference will be
that the damages under detrimental reliance is not based on contract
damages but rather only the actual cost expended in the work done.
Contract damages are based on the expectation of ones’ bargain or the benefit of ones’ bargain. It includes the cost of doing the work of the contract and the profit. But the damages awardable are based on detrimental reliance, only the cost of work done on the contract.
Based
on this advice, my friend pursued his payment with all amount of vigor
and luckily for him, he was one of the few contractors paid. He informed me that he was paid 18 million naira after unexplainable deductions. He
was expecting after completing 5.7 kilometers out of the 19 kilometers
of the contract to be paid 342 million based on the modified contract
price of 60 million naira per kilometer but he received N18 million.
Upon
the receipt of the 18 million naira, he paid up his mortgage loan to
the bank and moved back to his original station in Lagos. From
all indications, the few contractors paid, under Rochas Road Revolution
contracts, were paid based on detrimental reliance that is why no
contractor was paid anything close to 342 million naira which would have
been the actual contract amount based on the so called modification and
the 30% percent completion before payment contained in the alleged
original contract document.
However,
the overwhelming majority of the contractors who were not paid a dime
are now protesting and carrying placards around demanding for their
payment. These unfortunate and hapless Imo citizens have little or no chance of ever getting paid. The chances of any of these contractors winning a penny from a Lawsuit are “IFY” at best. The only chance of any of them getting a penny from the state government is through political negotiation. The question then is who would spend his political currency negotiating on behalf of these contractors? Many
of the Imo elder statesmen who could have negotiated on behalf of these
contractors believe that only their greed put then in their current
situation.
Speaking
to one of the known road contractors in the state, he said, “who, in
his right mind, unless blinded by greed, will go to a bank for facility
to execute a road contract without a contract document and an initial
mobilization fee?” He further said that government contracts are not done just based on trust because anything could happen at anytime. These contracts were entered into at the height of the tribunal litigation. What
if the tribunal nullified the election of Governor Rochas Okorocha,
what document will the contractors present as evidence of a contract
with the state when none of them is in possession of the contract
documents?”
One
of my heroes, my late father, Mr. Sebastian Chiedozie Okpalaeke told me
that, “Information is knowledge and knowledge is power, but only the
appropriate use of power, derived from knowledge is wisdom”
The
Imo State Government by its superior legal knowledge and negotiating
power perpetrated fraud to these hapless unfortunate citizen contractors
but to the detriment of the entire Imo State. December is the last month of the year. As
Ndigbo, we are known as sojourners all over the globe and at year’s
end, in December, many make the traditional annual pilgrimage from their
stations back to our land in the heartland of Igbo nation. As
a result of this annual pilgrimage back home, the previous Government
made it an annual project through IRROMA to grade every rural road in
all nooks and crannies of the State. This makes
our rural roads motorable, thereby easing the traffic of people and
goods, even with the increased number of vehicular traffic as a result
of this annual pilgrimage. But this year the situation will be different.
Without
IRROMA which has been rendered moribund and its assets nowhere to be
found even in the state, Imo will be lucky if the major rural roads are
graded. By the way, what happened to these Assets
of IRROMA valued at 12.5 billion naira by the United Nations
Development Agency in 2010?
Why
would any sane government enter into an agreement for the grading of
its rural roads at the cost of 60 million naira per kilometer when a
previous government did the same grading at zero cost to the
commonwealth of the people of the state?
Finally another hero of mine the legendary reggea artist Robert Nesta Marley (Bob Marley), in his song “Small Axe” said, that it is fool hardy to play smart without being clever. His exact words were “Playing smart, not being clever”. This is the only apt way to describe the deceit perpetrated on the Rochas Road Revolution contractors by the Imo Government.
It is written that Imo must be better, but how can Imo be truely better through official fraud and deceit? We must all therefore join hands and ensure that Imo is quickly returned back to the hands of God.
Dr. K.C.Okpaleke writes in from Owerri, Imo Statewp_posts
Related Posts
- Prostate: Nigerian hospital makes history, performs 1st Urolift surgery in Nigeria
- Gunmen shoot Chimezie, Nigerian barman, dead in Durban, South Africa
- ‘Tinubu pardoned 70 drug lords, it has never happened in world history’ – Dino Melaye
- How Benin Palace shut down ‘Iyaloja’ politics in Edo markets
- Super Eagles keep 2026 World Cup hopes alive with win over Lesotho
Short URL: https://newnigerianpolitics.com/?p=27115